Padma Bridge full structure construction completed: Quader

news-image

Road Transport and Bridges Minister Obaidul Quader said the construction work of entire structure of the much-awaited Padma Bridge has been completed with the installation of last girder on the viaduct at Mawa end in Munshiganj.

Quader, also Awami League general secretary, said this while speaking at a virtual view-exchange with BRTC and BRTA’s Sylhet Zone officials from his official residence in Dhaka.

He mentioned that the progress of construction works of the main bridge is 93.25 percent so far and river training works progress is 83 percent while the overall project progress reached 85.5 percent.

The minister hoped Padma Bridge would be opened for vehicular movement in June, 2022.